Petitioner South County Citizens for Smart Growth (Smart Growth) appeals from the trial court's denial of its petition for writ of mandate in which Smart Growth alleged that the County of Nevada (the County) violated various provisions of the California Environmental Quality Act (CEQA; Pub. Resources Code, § 21000 et seq.) in approving a commercial real estate project in Nevada County.
We will affirm the judgment.
This appeal arises from the County's decision to approve the Higgins Marketplace Project (the project) in southwestern Nevada County. Real Party in Interest KKP Lake of the Pines, LLC (KKP), submitted the application for the project to the County in 2005. The 20.07-acre site consisted of one parcel owned by the Tintle family, but KKP had an option to purchase the northern portion of the site. The original proposal involved subdivision of the site into 10 parcels for commercial, light industrial, and office uses. On five of the parcels (approximately 10.58 acres), the proposal called for a 59,800-square-foot retail store (expected to be a Bel-Air Market), two retail buildings (one 13,200 square feet and the other 6,500 square feet), two 3,500-square-foot drive-through fast-food restaurants, and 482 parking stalls. No development was proposed for four other parcels (approximately 5.07 acres), which would continue to be owned by the Tintle family, although the proposal allowed for future development of approximately 42,000 square feet of light industrial and office spaces. The last parcel, which was around 3.26 acres, was designated to retain existing wetlands and to provide a 25-foot buffer between the developed parcels and the onsite wetlands. The proposal also included a proposed habitat management plan, as required by the County Code because the wetland buffer was less than 100 feet.
In November 2007, the County published a draft EIR (draft EIR) analyzing the project's potential significant impacts on the environment, and identifying potentially feasible mitigation measures and alternatives that would minimize or avoid potential significant impacts. The draft EIR identified two significant traffic impacts and one significant cumulative air quality impact that could not be reduced to less than significant levels even with the implementation of the mitigation measures identified in the draft EIR. All other potentially significant impacts would be reduced to less than significant levels with the implementation of mitigation measures.
The County's environmental consultant prepared responses to the written and oral comments received at the hearing on the draft EIR. The final EIR — which consisted of the draft EIR, the responses to comments, and associated appendices — was released for public review on October 30, 2008. Following release of the final EIR, but prior to the Planning Commission's hearing on the document, four more comment letters were received, including a letter from Smart Growth's counsel. The County's environmental consultant prepared responses to the late comments, and the County included the late comments and the responses in an appendix to the final EIR.
On January 8, 2009, the Planning Commission held a hearing on the final EIR to consider whether to recommend that the Nevada County Board of Supervisors (the Board) (1) certify the final EIR, and (2) approve the legislative actions required for the project (including the general plan amendment and rezone). The staff report prepared for the Planning Commission hearing recommended that the Planning Commission vote to recommend that the Board approve a modified version of the project, the staff alternative, in order to address concerns over the project's air quality and traffic impacts. The staff alternative built upon alternative 4 in the draft EIR (the "Redesign/Reduced Density" alternative), which provided for a reduction in overall retail development. The staff alternative would cap commercial property at 75,000 square feet, have 10 acres of open space, increase the wetland buffer from 25 to 100 feet, and prohibit fast-food restaurants due to their high traffic generation. The Planning Commission voted three to two to recommend that the Board approve the staff alternative, and the Planning Commission unanimously voted to recommend that the Board certify the final EIR.
Thereafter, KKP worked to address the Planning Commission's concerns and revise the project based on the Planning Commission's recommendations. KKP submitted two alternatives that would reduce the project's footprint and eliminate fast-food restaurants. The overall number of proposed buildings was
The primary differences between the staff alternative and KKP's second alternative were that in KKP's second alternative (1) the Tintle family property was allowed to keep its existing business park designation on 3.03 acres and the proposed office professional designation on 0.78 acres; (2) the wetland setback would be 50 feet rather than 100 feet, but an additional 20 feet was added as a buffer, making the overall reduction to the setback only 30 feet; (3) the total square footage of community commercial designations was increased from 75,000 square feet to 75,800 square feet; and (4) open space was reduced by approximately four acres.
Consistent with the staff recommendation of KKP's second alternative (hereafter also referenced as the revised project), the proposed tentative parcel map was modified to coincide with the new site plan, with seven parcels divided as follows: one for each building, one for the wetlands/open space parcel, and two for the Tintle property parcels, which the Tintles intended to retain after the sale to KKP. In response to objections from the Tintles, the revised project would continue to allow the future development of their parcels for commercial uses as permitted by existing zoning standards. However, development would be limited to 26,000 square feet of building space.
On May 28, 2009, the Planning Commission held a meeting to consider (1) the details of the revised project, and (2) whether to recommend that the Board certify the final EIR. Due to a procedural error in noticing the meeting, the Planning Commission did not discuss the details of the revised project at that time. Instead, it voted five to zero that the final EIR adequately encompassed the revised project, and it recommended that the Board certify the final EIR. However, on June 11, 2009, the Planning Commission met again and discussed the details of the revised project. The Planning Commission voted to recommend that the Board approve the revised project (KKP's
On July 7, 2009, the Board held a public hearing to consider the final EIR, and whether to approve the associated legislative actions. Smart Growth's attorney submitted a lengthy comment letter on the final EIR at the beginning of the hearing. To allow time to consider the letter, the Board continued the meeting until mid-August. In light of the lengthy comment letter and other letters that were received, additional responses to comments were prepared and incorporated into the final EIR.
On August 18, 2009, the Board held two public hearings: one to consider the final EIR and the other to consider the legislative actions. The Board voted to certify the final EIR and approve the legislative actions.
Smart Growth timely filed a petition for writ of mandate in superior court. As relevant to the present appeal, Smart Growth asserted in a second amended petition that the County violated CEQA by (1) failing to prepare and recirculate a revised draft EIR with the staff alternative, which was a potentially feasible alternative and would have less impact on the environment than the revised project; (2) failing to make any findings or otherwise cite to substantial evidence explaining why the staff alternative should not or could not be approved; (3) asserting that traffic impacts were mitigated to "less than significant" levels by administratively redesignating an affected road as a minor arterial without any change to actual traffic conditions on the impacted road; and (4) finding that the revised project's impacts on traffic conditions would be less than significant. After reviewing the administrative record, the trial court rejected these contentions and denied the petition for writ of mandate.
Section 21168.5 provides that a court's inquiry in an action to set aside an agency's decision under CEQA "shall extend only to whether there was a prejudicial abuse of discretion. Abuse of discretion is established if the agency has not proceeded in a manner required by law or if the determination or decision is not supported by substantial evidence." The Guidelines define "substantial evidence" as "enough relevant information and reasonable inferences from this information that a fair argument can be made to support a conclusion, even though other conclusions might also be reached." (Guidelines, § 15384, subd. (a).)
"`The court does not pass upon the correctness of the EIR's environmental conclusions, but only upon its sufficiency as an informative document.'
Smart Growth contends the County violated CEQA's mandatory procedures by failing to prepare and recirculate a revised draft EIR with the staff alternative. Before addressing this contention, it will be helpful to set forth the relevant CEQA framework and address the difference between (1) the determination, during the scoping process, of whether to include alternative projects in the draft EIR and the adequacy of the chosen alternatives, and (2) the determination of whether to recirculate an EIR when significant new information is added concerning a feasible project alternative.
The range of alternatives that must be discussed and their level of analysis are subject to a "rule of reason." (Laurel Heights I, supra, 47 Cal.3d at p. 407; see Guidelines, § 15126.6, subd. (f) [an EIR must "set forth only those alternatives necessary to permit a reasoned choice"].) "`Absolute perfection is not required; what is required is the production of information sufficient to permit a reasonable choice of alternatives so far as environmental aspects are concerned.' [Citation.]" (Village Laguna of Laguna Beach, Inc. v. Board of Supervisors (1982) 134 Cal.App.3d 1022, 1029 [185 Cal.Rptr. 41] (Village Laguna).) The EIR is not required to set forth every conceivable alternative (Jones v. Regents of University of California (2010) 183 Cal.App.4th 818, 826-827 [108 Cal.Rptr.3d 6]), given that in some cases "there are literally thousands of `reasonable alternatives' to the proposed project." (Village Laguna, supra, 134 Cal.App.3d at p. 1028.)
The determination of whether to include an alternative during the scoping process is whether the alternative is potentially feasible (Mira Mar Mobile Community v. City of Oceanside (2004) 119 Cal.App.4th 477, 489 [14 Cal.Rptr.3d 308] (Mira Mar)), and the EIR "is required to make an in-depth discussion of those alternatives identified as at least potentially feasible." (Sierra Club v. County of Napa (2004) 121 Cal.App.4th 1490, 1505, fn. 5 [19 Cal.Rptr.3d 1], italics omitted.) Differing factors come into play when the final decision on project approval is made; at that juncture the decisionmaking body evaluates whether the alternatives are actually feasible. (Guidelines, § 15091, subd. (a)(3).) "[T]he decision makers may reject as infeasible alternatives that were identified in the EIR as potentially feasible." (California Native Plant Society v. City of Santa Cruz (2009) 177 Cal.App.4th 957, 981 [99 Cal.Rptr.3d 572].)
An express finding is not required on whether new information is significant; it is implied from the agency's decision to certify the EIR without recirculating it. (Laurel Heights II, supra, 6 Cal.4th at p. 1133 ["CEQA does not require an express order or finding on the subject of whether to recirculate a final EIR."]; Western Placer Citizens for an Agricultural & Rural Environment v. County of Placer (2006) 144 Cal.App.4th 890, 904 [50 Cal.Rptr.3d 799] (Western Placer Citizens) [a written finding is not required; "[b]y certifying the [final EIR], the Board necessarily concluded the new information did not require recirculation and additional public comment"].) Furthermore, "all new information occurring after release of the final EIR but prior to certification and project adoption need not be included in the EIR before the agency determines whether the new information is significant so as to trigger revision and recirculation." (Western Placer Citizens, supra, 144 Cal.App.4th at p. 902.)
After the final EIR had been circulated, the Planning Commission voted to recommend that the Board certify the final EIR and approve the staff alternative. Thereafter, however, KKP submitted its second alternative addressing some of the Planning Commission's concerns; KKP's second alternative was recommended by Planning Commission staff and the Planning Commission as the revised project; and the Board ultimately approved the revised project.
Under its first argument heading, Smart Growth does not challenge the adequacy of the various alternatives that were included and discussed in the draft EIR as a result of the scoping process. Nor does Smart Growth challenge the County's failure to recirculate the final EIR with a discussion of the revised project.
Smart Growth bears the burden of proving a double negative, that the County's decision not to revise and recirculate the final EIR is not supported by substantial evidence. (Western Placer Citizens, supra, 144 Cal.App.4th at p. 903; Sierra Club v. County of Napa, supra, 121 Cal.App.4th at p. 1497.) That is, Smart Growth must demonstrate that there is no substantial evidence to support a determination that the staff alternative was not significant new information. (Guidelines, § 15088.5, subd. (a)(3).) For the staff alternative to be significant new information, it must be feasible; it must be considerably different from other alternatives previously analyzed; it must clearly lessen the significant environmental impacts of the proposed project; and the project's proponents must decline to adopt it. (Ibid.) Smart Growth has the burden to demonstrate that there is no substantial evidence to support a negative finding on any of these factors in order to establish that the County abused its discretion in failing to recirculate the EIR.
"As with all substantial evidence challenges, an appellant challenging an EIR for insufficient evidence must lay out the evidence favorable to the other side and show why it is lacking. Failure to do so is fatal. A reviewing court will not independently review the record to make up for appellant's failure to carry his burden. [Citation.]" (Defend the Bay v. City of Irvine (2004) 119 Cal.App.4th 1261, 1266 [15 Cal.Rptr.3d 176].)
Alternative 1 was the "No Project" alternative required by CEQA. (Guidelines, § 15126.6, subd. (e).) In that alternative the site would be left in its current condition.
Alternative 2, the "Woodridge Court Right-In, Right-Out" alternative, provided for restricted "right-in and right-out" access to the project from Woodridge Court. This alternative was selected to determine whether restricted access would avoid traffic impacts to State Route 49.
Alternative 3, the "Business Park Land Use" alternative, would develop the project under the current general plan land use designations. This alternative was designed to reduce traffic and noise impacts to nearby residences.
Smart Growth argues that the staff alternative "is considerably different" from the alternatives considered in the draft EIR, because none of the draft EIR's alternatives "meet the project's stated objectives by providing for the development of a full-service shopping alternative that would improve the County's jobs/housing balance, while simultaneously reducing the Project's acknowledged `significant and unavoidable' cumulative air quality impacts by designating the remainder of the project site as Open Space." (Italics omitted.) Smart Growth claims that none of the alternatives presented during the County's administrative consideration of the project "contemplates this potentially feasible way to reduce the project's air quality impacts. Rather, every action alternative considered in the publicly circulated Draft EIR reserves a substantial portion of the project site for future, business park and office uses (which are not among the Draft EIR's stated Project objectives), which necessarily include these land uses' attendant incremental future contributions to cumulative air quality impacts." (Italics & fn. omitted.)
With respect to another recirculation factor, Smart Growth simply asserts that the staff alternative will "clearly lessen the significant environmental impacts of the [proposed] project" (Guidelines, § 15088.5, subd. (a)(3)) by designating four acres as open space on the Tintle property, rather than permitting future business park and professional use, and by eliminating the fast-food restaurants. Smart Growth provides no analysis, supported by citations to evidence in the record, explaining how this will clearly lessen the project's environmental impacts. For example, the reduction in cumulative air quality environmental impacts might be insignificant when viewed under the appropriate thresholds for Nevada County. Moreover, Smart Growth fails to show that the staff alternative clearly lessens the significant environmental impacts of the revised project; instead, Smart Growth compares the staff alternative to the project as originally proposed.
We are not required to cull through the more than 11,000-page administrative record to see if there is support for Smart Growth's position. (Defend the Bay v. City of Irvine, supra, 119 Cal.App.4th at pp. 1265-1266.) Under the circumstances, Smart Growth has not established its claim that the County abused its discretion in failing to prepare and recirculate a revised draft EIR with the staff alternative.
In a related contention, Smart Growth claims the County violated CEQA's mandatory procedures by failing to make findings regarding the feasibility of the staff alternative. Smart Growth believes that once the Planning Commission found the staff alternative sufficiently feasible to recommend approval of
Furthermore, although the lead agency must give reasons for rejecting the alternatives discussed in the EIR where the document identifies one or more significant environmental effects of the project (§ 21081, subd. (a)(3); Guidelines, § 15091, subd. (a)(3)), the staff alternative was not one of the alternatives discussed in the EIR and Smart Growth has not established that the County erred by not including it in the EIR.
Smart Growth does not point to any CEQA statutes or regulations requiring that the lead agency make findings regarding why it rejected an alternative proposed after the final EIR and not included in the EIR. (South Orange County Wastewater Authority v. City of Dana Point (2011) 196 Cal.App.4th 1604, 1617 [127 Cal.Rptr.3d 636] ["The Legislature has expressly forbidden courts to interpret CEQA or the [CEQA Guidelines] to impose `procedural or substantive requirements beyond those explicitly stated' in the act or in the guidelines."].) Indeed, as we explained in part I, the County was not required to make an express finding of infeasibility. It was only required to find that the staff alternative was not significant new information, a finding that may be implied from its decision to certify the EIR without recirculating it. (Laurel Heights II, supra, 6 Cal.4th at p. 1133; Western Placer Citizens, supra, 144
Smart Growth contends the County's failure to make findings explaining why the staff alternative was infeasible "cannot be squared with" Laurel Heights I, supra, 47 Cal.3d 376, and Goleta II, supra, 52 Cal.3d 553, but those cases are inapposite.
Laurel Heights I, supra, 47 Cal.3d 376 concerned an EIR's inadequate discussion of alternative locations for a project in violation of Guidelines section 15126. The Regents of the University of California merely included a conclusory statement that any alternatives were infeasible without providing supporting analysis. (47 Cal.3d at pp. 403-404.) The California Supreme Court held that the Regents must include their analytic route so that the public can be fully informed, rather than simply expecting the public to trust them. (Id. at pp. 404-405.) But here, adequate alternatives were discussed in the EIR. Laurel Heights I has no bearing on the present claim that the County had an obligation under CEQA to issue a finding of infeasibility if it chose not to recirculate the EIR with the staff alternative.
Goleta II, supra, 52 Cal.3d 553 arose following a first appeal in which the county's EIR was held to be inadequate because it failed to discuss any alternative project sites. (Citizens of Goleta Valley v. Board of Supervisors (1988) 197 Cal.App.3d 1167, 1180 [243 Cal.Rptr. 339] (Goleta I).) During the pendency of the appeal in Goleta I, the county began preparation of a supplemental EIR which contained a discussion of only one alternative site. (Goleta II, supra, 52 Cal.3d at pp. 560-561.) A citizens group, CGV, belatedly requested consideration of a number of additional sites. (Id. at p. 562.) The board of supervisors concluded none of the alternative sites were feasible and issued 10 pages of findings concerning those alternative sites, but a discussion of the additional alternatives was not included in the EIR. (Id. at pp. 562, 567-570.) The Court of Appeal concluded that the EIR failed to delineate facts sufficient to explain its rejection of alternative sites other than the single alternative discussed in the EIR. (Id. at p. 563.)
The California Supreme Court reversed the Court of Appeal, holding that it was reasonable to explain why the alternative sites were rejected via administrative findings, rather than in the EIR, due to the belated manner in which the sites were brought to the county's attention. (Goleta II, supra, 52 Cal.3d at pp. 567-570.) The Supreme Court stated: "In general, an EIR should set forth the alternatives that were considered by the lead agency and rejected as
"Thus, where the circumstances warrant, a reviewing court may consult the administrative record to assess the sufficiency of the range of alternatives discussed in an EIR. The circumstances justify such consultation here. Unlike the EIR in [Laurel Heights I], County's environmental review of the ... project discussed a full range of alternatives, including an in-depth discussion of one off-site alternative. Moreover, CGV raised the issue well after the comment period had expired. Thus, the Board's decision to delineate its reasons for rejecting the CGV sites as feasible alternatives by means of administrative findings, rather than a full-blown supplemental EIR, cannot be deemed in this case to have been erroneous." (Goleta II, supra, 52 Cal.3d at pp. 569-570.)
Smart Growth next contends the County violated CEQA by relying on future traffic improvements that have not been approved yet in order to declare the revised project's traffic impacts less than significant.
Smart Growth contends the County relied on uncertain future traffic improvements in order to declare the project's level of service (LOS) impact on Combie Road to be less than significant. Smart Growth states that KKP submitted a revised traffic study indicating that the revised project would cause Combie Road, between Higgins Road and State Route 49, to drop to LOS F under its existing designation as a "major collector." LOS F is the worst level of traffic flow.
However, a traffic engineer for the County's traffic consultant indicated that the fact a section of Combie Road near the project has more driveways than other sections of the road must not be taken out of context, and does not dictate the designation of the road. The traffic engineer stated, "It is impractical to consider separate designations of small sections of roadways within larger designated roadway segments. Designating roadways in such a piecemeal manner would defeat the purpose of corridor designations." In other words, the existing driveways on one portion of Combie Road would not preclude a minor arterial designation for the entire roadway.
The trial court concluded, and we agree, that the County did not require the redesignation of Combie Road as a minor arterial as a mitigation measure. The County simply determined that, for purposes of the traffic analysis, Combie Road functioned as a minor arterial because it acts as a thoroughfare between Lake of the Pines and State Route 49. It did not function as a major collector, which allows unlimited driveway accesses and therefore results in slower conditions. Indeed, independent of the project, the County submitted a change in designation of Combie Road to California's Department of Transportation (Caltrans) for use on federal functional class maps, and the impetus to reclassify the road came out of the 1996 general plan. Accordingly, the
Smart Growth fails to establish in its opening brief that there is no substantial evidence to support the County's determination that Combie Road functions as a minor arterial. It also fails to dispute the appropriateness of basing the EIR's traffic impact determination on roadway function rather than designation. Although the County intends to widen Combie Road and the project is fully funded, this fact was simply cited in the administrative record as support for the conclusion that Combie Road functions more as a minor arterial than a major collector. But because the road functions as a minor arterial, the project will have a less than significant impact on the road, which is why it was not necessary to condition the project on the road's future expansion. (§§ 21002, 21081; Guidelines, §§ 15002, subd. (a)(3), 15091, subd. (a)(1).)
Under the circumstances, Smart Growth's claim that the County violated mandatory CEQA provisions lacks merit.
The judgment is affirmed.
Raye, P. J., and Robie, J., concurred.